11
Operating and Safety Instructions
4. TRANSPORT OF THE MACHINE
* The transport should be done by qualified personnel only.
4.1. The machine should be transported by lifting with proper equipment (not
touching the ground during the transport).
4.2. The Machine is delivered wrapped in nylon as packaging, unless other form
of packing is agreed upon with the
customer.
4.3. For the weight and overall dimensions of the machine see Page 32.
5. INSTALLATION OF THE MACHINE
Necessary air and electrical facilities should be organized by the customer.
5.1. PREPERATION
5.1.1. The machine's dimension are shown in the Technical Features page (Page
33). The ground, where the machine will be placed, should be even, solid
enough to bear the weight of the machine.
5.1.2. The machine should be located approx. 50 cm away from the back wall.
5.1.3. As a conveyor will be installed to its lateral surface, you should leave a
distance equal to the conveyor length
5.2. ELECTRIC CONNECTION
5.2.1 The three-phase electric cable socket has to be in accordance with the
socket on the machine.
5.2.2 The operating voltage is 400V 50 Hz. Check the supply voltage.
5.2.3 Use grounded sockets.
5.2.4. Check the supply voltage. The supply voltage must be in accordance with
the data stipulated on the machine’s type label.
5.2.5. The electric connections have to be made by a qualified electrician, the
rotation direction of the milling cutters has to be observed by starting the
machine. If the milling cutters rotate in reverse direction, the socket connections
have to be checked and re-connected properly.
Comentários a estes Manuais